How Guernsey's land is changing: where the next 2,000 homes could go

How Guernsey's land is changing: where the next 2,000 homes could go
  • Guernsey's Housing Site Availability Framework lists 67 sites with capacity for 1,741 homes, with 205 already under construction as of March 2026
  • The States approved nine new Priority Affordable Housing sites this week, adding an estimated 267 homes and bringing the total pipeline to 2,008 homes across 76 sites
  • Leale's Yard largest site at 314 homes
  • Evidence showed a surplus of 665 private homes above target but a shortfall in affordable housing, which the nine new sites are designed to address, creating a projected surplus of 72 affordable homes
  • The States rejected two proposed caps on development density and approved creation of a development framework for the L'Aumone redevelopment area, which could provide 160 additional affordable homes on hospital sites
audio-thumbnail
Listen to this article
0:00
/0

Part four of our series mapping how Guernsey's land is changing.

Today: every site in the States' Housing Site Availability Framework, with its stage and planning history, and the nine new affordable housing sites. In March, sites with 205 of those homes were under construction. This week the States agreed where the next affordable homes should go.

The States' first Housing Site Availability Framework, published in March 2026, lists 67 sites with room for 1,741 homes.

At the time it was published, sites with 205 of those homes were under construction.

Add the nine sites the States designated for affordable housing on Tuesday, with an estimated 267 homes, and the pipeline stands at 2,008 homes on 76 sites.

324 homes were on sites with planning permission and 70 on one site preparing to build. The remaining 1,142 were on sites without permission: potential sites, sites where planning work was under way, or sites with an application ready.

The framework gives each site's stage at three points: the third quarter of 2025, the fourth quarter, and March 2026. Over those six months, 22 of the 67 sites moved forward a stage. One went backwards: the English & Guernsey Arms went from permission granted to potential site.

The biggest single move was Parc Le Lacheur, 180 affordable homes, which went from potential site to planning work under way.

Parc Le Lacheur

Mostly private, mostly small

In the March framework, 52 of the 67 sites are listed as private housing, with 753 homes between them.

Only three sites, with 264 homes, are listed as affordable housing, and two more are mixed.

Tenure for the remaining ten sites, including Leale's Yard, the largest at 314 homes, is still to be decided.

That balance has shifted since: all nine sites the States designated on Tuesday are for affordable housing, adding an estimated 267 affordable homes.

The framework is the States' own assessment at a point in time.

The former L'Eree Hotel, listed as under construction, has been demolished, the site cleared, and a revised scheme for the 15 flats was submitted in October.

The former L'Eree Hotel site

What the States decided

The Island Development Plan decides which land can be used for housing.

The review the States approved on Tuesday is mainly about making sure there is enough land for the affordable homes the island needs.

The States' housing indicator says the island needs 1,488 new homes between 2024 and 2028, 673 of them affordable. With buffers added, the DPA plans land for 1,062 private and 976 affordable homes to 2030.

Its evidence shows a surplus of land for private housing, 665 homes more than needed, but a shortfall for affordable housing.

Its main answer is nine Priority Affordable Housing sites, expected to provide about 267 affordable homes. The States approved all nine on Tuesday. With them, the DPA says, affordable supply exceeds the target by 72.

SiteParishHomesVote
Whispers VineryCastel4023–10
School Lane VinerySt Martin's4032–1
Regency VinerySt Martin's3927–5
Former Fletcher's Freesias, Route CarréSt Sampson's3228–4
Selbourne VinerySt Peter Port3130–3
Two AcresForest2628–4
Springhurst HouseForest2232–1
Land at Sandy HookSt Sampson's2222–9
Les Caches FarmSt Pierre du Bois1530–3

Homes: DPA estimate of affordable homes. Vote: States of Deliberation, 24 November 2026, for and against. Whispers was voted on with the Vazon local centre.

The policy now expects planning permission to be secured on each by the end of 2027, with a mechanism to take sites away and replace them if they do not progress.

They are on the map in purple.

The States rejected both caps the DPA proposed. Amendment 6, limiting Whispers to 40 homes against an assessed capacity of 53, was lost by 24 votes to 6.

Amendment 5, limiting Two Acres to 15 against 26, was lost by 23 votes to 6.

The framework already includes the Castel Hospital, King Edward VII Hospital and Perruque House as potential sites with no number of homes yet.

The review puts them inside a new redevelopment area at L'Aumone, and the DPA's January 2026 housing land supply update, quoted in the inspector's report, estimates the hospital sites, with the Princess Elizabeth Hospital, could provide 160 affordable homes.

Amendment 3, from Deputies Steve Williams and Sasha Kazantseva-Miller, was carried by 33 votes to none.

It directs the DPA to produce a development framework for the area by June 2028, with up to £200,000 from the budget reserve, and the Committee for Housing to produce a master plan.

The framework is meant to be updated twice a year. The Quarry will update the map when it is.

Coming up: Hotels into homes

Q&A

Q: How many homes are in Guernsey's housing pipeline and across how many sites?
A: The pipeline currently stands at 2,008 homes across 76 sites. This includes 1,741 homes on 67 sites listed in the March 2026 Housing Site Availability Framework, plus 267 homes on nine new Priority Affordable Housing sites approved by the States this week.

Q: What is the breakdown between private and affordable housing in the development pipeline?
A: Of the 67 sites in the framework, 52 are designated for private housing with 753 homes, only three sites are for affordable housing with 264 homes, two are mixed-use, and ten sites including the largest (Leale's Yard with 314 homes) have tenure yet to be decided. The DPA's analysis shows a surplus of 665 private homes but previously had an affordable housing shortfall.

Q: What is the L'Aumone redevelopment area and what housing potential does it have?
A: L'Aumone is a new redevelopment area that includes the Castel Hospital, King Edward VII Hospital, Perruque House, and the Princess Elizabeth Hospital. These hospital sites are estimated to provide 160 affordable homes. The States approved an amendment directing the DPA to produce a development framework for the area by June 2028 with up to £200,000 in funding.